I. Group
ADMINISTRATIVE COMPLIANCE
Criteria Leads to rejection Автоматична оценка Prioritization
1.
The Application Form is signed with a QES (according to the Application Guidelines) by the official representative of the applicant or a duly authorized person
Yes No No
2.
When the Application Form is signed by a person other than the official representative, the relevant authorization is provided
Yes No No
3.
The Application Form is completed in English (in UMIS 2020) and in Bulgarian (as an attachment)
Yes No No
4.
All mandatory fields in the Application Form are filled in with the relevant information
Yes No No
5.
The project duration does not exceed the maximum duration described in the Application Guidelines
Yes No No
6.
The Application Form includes performance indicators that  are quantified and meet the requirements of the Application Guidelines
Yes No No
7.
A risk analysis is attached in filled-in Risk matrix format
Yes No No
II. Group
ELIGIBILITY ASSESSMENT
Criteria Leads to rejection Автоматична оценка Prioritization
1.
The overall objective of the project is in line with the Application Guidelines
Yes No No
2.
The Applicant meets the eligibility criteria set out in the Application Guidelines
Yes No No
3.
The foreign project partner/s (if any) meets the eligibility criteria set out in the Application Guidelines
Yes No No
4.
The Bulgarian partner/s (if any) meets the eligibility criteria set out in Application Guidelines
Yes No No
5.
CVs (description of the professional experience) of the project management team members are presented
Yes No No
6.
The declarations of legal compliance of the Applicant and the partner/s are provided
Yes No No
7.
The declaration for the participation of consultants in the preparation of the project proposal is provided
Yes No No
8.
The declaration for identical copies of documents in Bulgarian and English is provided by the Applicant
Yes No No
9.
The declaration on the VAT status of the Applicant and the partner (if spending money) is provided
Yes No No
10.
The declaration of the origin of the financial contribution (if applicable) of the applicant and partner/s is provided
Yes No No
11.
The Communication Plan is attached
Yes No No
12.
A (Draft) Partnership Agreement/a Letter of intent  (if applicable) - according to the template in the Application Guidelines - is provided
Yes No No
13.
Strategy for the development of the Youth Centre for the next 10 years is provided
Yes No No
14.
Link to the financial documents of the applicant is provided (in case there is no link provided, the actual documents are attached to the project proposal)
Yes No No
15.
Balance sheet for the preceding year of the partner/s is provided (if applicable), except in the case when the partner is from a donor state
Yes No No
16.
Evidences of operational capacity (copies of contract/s or equivalent document/s) are provided
Yes No No
17.
The budget (part of the UMIS 2020 Application Form) is presented in BGN
Yes No No
18.
The budget (in Excel version) in BGN and EUR is presented as attachments in UMIS 2020
Yes No No
19.
The envisaged project grant is in accordance with the defined minimum and maximum limits under the application procedure
Yes No No
20.
The amount of management costs is up to 8% of the total eligible costs
Yes No No
21.
A Decision by the Municipal Council is attached - approving the application under the present procedure and confirming a commitment to ensure sustainability of the project according to the requirements
Yes No No
22.
In case of construction and repair works/reconstruction and/or other activities related to construction and repair works on the Applicant's own land/buildings/estates, there is attached an Act for municipal property and a Decision of the Municipal Council for permission to use the terrain/building/estate for the project objectives
Yes No No
23.
In case of construction and repair works/reconstruction, the required documents are supplied according to the Application Guidelines
Yes No No
24.
The cost of construction and repair works/reconstruction and equipment is up to 60% of the total eligible costs
Yes No No
25.
The method for defining the indirect costs is chosen in accordance with Art. 8.5.1, points a), b), c), d) and e) of the Regulation on the implementation of EEA FM 2014-2021
Yes No No
III. Group
CONCLUSION
Criteria Leads to rejection Автоматична оценка Prioritization
1.
The project is admitted for consideration at the "Technical and Financial Assessment" stage
Yes No No